UPDATE- Florie Farm Road Improvements

The Florie Farm Road project has experienced some delays due to the availability of materials.  Based on this, it is anticipated that the drainage work will be completed in the next 3 to 4 weeks as the material comes in.  The paving will be delayed until the spring when favorable weather conditions will allow the road to be paved.  An additional notice will be provided before the paving commences.